3WDT was a directional drilling project that ABC Civil Group completed as a contractor for Service Stream developing the NBN network. ABC Civil Group was the sole civil contractor, this build involved ABC installing 41 km of P50 and P100 conduit across Wonga Park, Park Orchards and Warrandyte. This project incorporated a majority of civil works in private properties throughout the area. For this reason, communication to the residents, civil design and as-built drawings, as well as reinstatement requirements, were imperative for efficient operations and the required customer relations. The project started in June 2018 and ran through to December 2019.
Significant communication to the many stakeholders applicable in the build turned out to be a substantial asset throughout the duration of the project. The varying conditions outlined by the residents meant ABC had to alter site-specific procedures and adapting new processes to mitigate this was instrumental in the competent completion of 3WDT.